County Road 70 at Interstate 35
Ames Construction was contracted to complete a 2 phase highway
project in Lakeville, Minnesota. During phase one, the highway
interchange at County Road 70 and Interstate 35 will be upgraded and
expanded along with a 1 mile stretch of County Road 70. The frontage
roads will be realigned and sewer work will be completed. Phase 2 will see
the existing bridge over I35 demolished and rebuilt with the remaining
portion of County Road 70 completed.
The project was completed during the fall of 2009.
Equipment
Caterpillar: MT835 with E-Ject 22, MT835 with E-Ject 22 with GPS,
   MT845 with E-Ject 22, MT865B with E-Ject E/22XW, D5Glgp, D6Hlgp,
   D6Rlgp, D6Rxw with GPS, 140H, 140Mawd with GPS, 345Bl, 345Cl,
   950F with bucket and forks, 966G, PS150B.
Dynapac: CA262 padded and smooth drum, CP14.
John Deere: 644J with bucket and forks, 8560 with Wil-Rici disk.
TEI: 2000.
Wacker: RT.
April 2009
October 2008
September 2008